217. The reconditioning technical program must contain
(1)  the name and contact information of the engineer responsible for the technical program;
(2)  the name, profession and functions of the persons who prepared or revised the program;
(3)  a chronological and detailed description of the work to be carried out;
(4)  the classification of the well determined according to Schedule 1;
(5)  the name and contact information of the enterprises charged with carrying out the work;
(6)  the demonstration that the regional and local geology and the presence of adjacent wellbores have been taken into consideration;
(7)  the reasons justifying the reconditioning;
(8)  the purpose of the reconditioning;
(9)  a lateral section of the well indicating the technical elements;
(10)  the list of pressure and leak tests, and the list of other tests planned;
(11)  the list of well logs planned;
(12)  the type of service rig and equipment to be used and their specifications;
(13)  the intervals to be the subject of reconditioning;
(14)  a description of the fluids used;
(15)  the pressure at the closed wellhead and the shut-in pressure of the well;
(16)  the demonstration that the equipment, components and casings may withstand the different stresses to which they will be submitted, in particular, bursting, collapse and tension stresses;
(17)  if applicable, a cementing program including, in particular,
(a)  the type of cementing;
(b)  the cementing intervals;
(c)  the method for applying the cement;
(d)  the type of cement, its density, its additives and their proportions, the setting time, the flow and pressure used;
(e)  if applicable, the maximum pressure for injecting the cement; and
(f)  if applicable, the changes to the cement required, if applicable, due to specific physical and chemical conditions of the environment, or to give the cement specific properties;
(18)  a well integrity verification and follow-up program;
(19)  any specific condition that could affect the safety of the work on the well;
(20)  an evaluation of the impact of the proposed work on the optimal recovery of the resource;
(21)  if applicable, the list of licences, certificates and other authorizations to be obtained;
(22)  the list of references used during the preparation of the technical program, in particular, the standards from recognized organizations and guidelines from other Canadian jurisdictions; and
(23)  any other information or document deemed necessary by the Minister.
Where work is planned in a temporarily closed well, the technical program must also contain the annual inspection worksheet provided for in Schedule 2.
O.C. 1252-2018, s. 217.
In force: 2018-09-20
217. The reconditioning technical program must contain
(1)  the name and contact information of the engineer responsible for the technical program;
(2)  the name, profession and functions of the persons who prepared or revised the program;
(3)  a chronological and detailed description of the work to be carried out;
(4)  the classification of the well determined according to Schedule 1;
(5)  the name and contact information of the enterprises charged with carrying out the work;
(6)  the demonstration that the regional and local geology and the presence of adjacent wellbores have been taken into consideration;
(7)  the reasons justifying the reconditioning;
(8)  the purpose of the reconditioning;
(9)  a lateral section of the well indicating the technical elements;
(10)  the list of pressure and leak tests, and the list of other tests planned;
(11)  the list of well logs planned;
(12)  the type of service rig and equipment to be used and their specifications;
(13)  the intervals to be the subject of reconditioning;
(14)  a description of the fluids used;
(15)  the pressure at the closed wellhead and the shut-in pressure of the well;
(16)  the demonstration that the equipment, components and casings may withstand the different stresses to which they will be submitted, in particular, bursting, collapse and tension stresses;
(17)  if applicable, a cementing program including, in particular,
(a)  the type of cementing;
(b)  the cementing intervals;
(c)  the method for applying the cement;
(d)  the type of cement, its density, its additives and their proportions, the setting time, the flow and pressure used;
(e)  if applicable, the maximum pressure for injecting the cement; and
(f)  if applicable, the changes to the cement required, if applicable, due to specific physical and chemical conditions of the environment, or to give the cement specific properties;
(18)  a well integrity verification and follow-up program;
(19)  any specific condition that could affect the safety of the work on the well;
(20)  an evaluation of the impact of the proposed work on the optimal recovery of the resource;
(21)  if applicable, the list of licences, certificates and other authorizations to be obtained;
(22)  the list of references used during the preparation of the technical program, in particular, the standards from recognized organizations and guidelines from other Canadian jurisdictions; and
(23)  any other information or document deemed necessary by the Minister.
Where work is planned in a temporarily closed well, the technical program must also contain the annual inspection worksheet provided for in Schedule 2.
O.C. 1252-2018, s. 217.